Park Lawn's westbound Gardiner on-ramp reopens two months early

The Park Lawn Road westbound on-ramp to the Gardiner reopened at 6 a.m. Friday, two months ahead of schedule, the City says.


The westbound on-ramp from Park Lawn Road onto the Gardiner Expressway is open again, two months sooner than the City of Toronto had planned. Crews cleared the ramp to traffic at 6 a.m. Friday, after finishing a bridge replacement over Mimico Creek ahead of schedule.

About 15,000 drivers use that ramp on a typical day, including trucks headed to the Ontario Food Terminal and to businesses farther west. The work started in August and was originally expected to take six months. The City says incentives and around-the-clock shifts — the same approach used on the Gardiner between Dufferin Street and Strachan Avenue — cut the job to four.

“The Park Lawn on-ramp is back open, and that’s good news for the 15,000 drivers who rely on it every day,” Mayor Olivia Chow said in the City’s announcement. “Commuters can get where they need to go faster, and truck drivers can get goods to the Ontario Food Terminal and businesses across the region.”

One piece of a longer Gardiner rebuild

The ramp sits in a larger repair program. The single-lane span over Mimico Creek was among five bridges pulled into an early-works contract for the third section of the City’s Gardiner Expressway Strategic Rehabilitation Plan, the stretch from Highway 427 to the Humber. The City says the full rebuild of that section is expected to start in 2028.

City Council approved the overall plan in 2016 as a six-part state-of-good-repair program for a highway that has been carrying traffic for more than 60 years. Weather, road salt and heavier loads have pushed it toward the close of the life it was designed for. The first section was finished in 2021 and the second in 2025.

Under the Ontario-Toronto New Deal, the province is set to take over the Gardiner and the Don Valley Parkway in the fall of 2027. Until then, Ontario is providing up to $353 million for operating and upkeep. Transportation Minister Prabmeet Sarkaria, quoted in the same release, called the early reopening “another win for drivers and businesses across the GTA” and pointed to that funding.

Deputy Mayor Amber Morley, who represents Etobicoke-Lakeshore, said the ramp’s return would be welcome news for residents and businesses in the area, and for the commercial traffic it carries.