The first new boat in the Toronto Island ferry fleet in more than 60 years is nearly here. In a media advisory on Wednesday, the City of Toronto said Lady of the Quays, its first electric ferry, was scheduled to reach the harbour in the coming days.
It is the first of two all-electric vessels the City is adding. Once the boat ties up at the Jack Layton Ferry Terminal, crews will begin commissioning and training. Passengers should not expect to ride until the spring. Officials from City Hall, Toronto Hydro and CreateTO held a briefing on Thursday at City Hall to update reporters on shore-side charging gear and what happens after the ferry arrives.
A year-round replacement for the Ongiara
The City’s project page says the vessel is crossing the Atlantic on the heavy-lift ship Happy Ranger. It was built by Damen at a yard in Galati, Romania, to plans from Concept Naval, a Quebec City firm. The City describes the pair as Canada’s first custom-built, fully electric ferries. Residents chose the names in a public vote last spring; Lady of the Quays received about 15 per cent of the 17,700 ballots.
Lady of the Quays is meant to run year-round and can break ice. The City says it is expected to carry as many as 650 people plus 14 vehicles — or two large trucks — and as many as 1,300 people with no vehicles aboard. That is roughly triple the capacity of the Ongiara, the 1963 boat it will replace, and the only vehicle ferry in the current fleet certified for icy water.
A second electric ferry, the passenger-only Toronto Islander, is still under construction and is slated to arrive in the second quarter of 2027. It is meant to replace the William Inglis. The four main boats now on the run are between 61 and 90 years old, not counting the heritage ferry Trillium, and together they carry about 1.4 million passengers a year.
Charging at the terminal, not on the Island
New charging towers are being installed at Jack Layton Ferry Terminal, a project CreateTO is managing. The City says a full charge for a round trip takes about six minutes, and that each boat will typically plug in whenever it docks on the mainland, even though the batteries are designed to handle four round trips on one charge. Island docks will not need charging equipment. Regular passenger service is expected to continue during the work; commercial vehicle trips to the Islands could face occasional interruptions.
Commissioning, including lake trials and crew training, is scheduled for the first half of 2027, according to the City’s timeline, ahead of the spring passenger debut.
Source: City of Toronto


Comments